Hydrogen transportation cost depends more on how much you move than on how far you move it. In the worked example below, built on U.S. Department of Energy (DOE) equipment costs, a buyer taking 10 tonnes a day over 100 km pays about $0.87/kg by compressed-gas truck against $1.57/kg for a new dedicated pipeline, but at 19 tonnes a day or more the pipeline becomes cheaper at that distance.
Short answer: For an industrial site taking 10 t/day of hydrogen 100 km from the electrolyzer, tube-trailer trucks add about $0.87/kg and a new pipeline about $1.57/kg on DOE cost data and stated illustrative assumptions. Pipelines win once volume passes roughly 13–24 t/day at 50–200 km, so size the route to the contract volume, not the map.
This article sits in our offtake and delivered-cost cluster. If you are still agreeing what the buyer must take and where title transfers, start with the hydrogen offtake agreement checklist.
Why does the delivery route matter to a hydrogen buyer?
A plant-gate price is not what an offtaker pays: the delivered price adds compression, transport and any storage between the electrolyzer and the user's fence. In the worked example below, transport alone adds $0.47–2.62/kg at 10 t/day, which can decide whether a deal works.
The question usually arrives as "pipeline or truck?" because those are the two realistic options for gaseous hydrogen over regional distances. The IEA's The Future of Hydrogen (2019) notes that "Today hydrogen distribution mostly relies on compressed gas trailer trucks for distances less than 300 km," and finds that for distances below 1,500 km, moving hydrogen as a gas by pipeline is likely to be the cheapest delivery option (IEA, The Future of Hydrogen, 2019). Both statements are true at once: trucks dominate today because most volumes are small, and pipelines win when volumes are large.
What is the hydrogen transportation cost by truck and by pipeline?
DOE publishes status values and targets for delivery equipment, which give a transparent starting point (DOE, Technical Targets for Hydrogen Delivery):
| Item (DOE FY2015 status) | Value |
|---|---|
| Gaseous tube trailer payload | 720 kg H2 at 250 bar |
| Tube trailer purchased capital cost | $720 per kg of payload |
| Transmission pipeline capital (8-inch equivalent, excluding right-of-way) | $765,000 per mile |
| Distribution pipeline capital (1-inch, excluding right-of-way) | $355,000 per mile |
| Tube-trailer terminal compressor (300 kg/h, 100 bar in, 550 bar out) | $450,000 uninstalled; 1.1 kWh/kg |
| Pipeline compressor specific energy (20 bar in, 100 bar out) | 0.82 kWh/kg |
Payload is the number to watch for trucks. The IEA notes that a trailer with lightweight composite cylinders can in theory carry up to 1,100 kg of hydrogen, but that in the United States "the pressure limit for steel tubes means that a trailer has a maximum load of 280 kgH2" (IEA, 2019). DOE's 2020 target was a 1,100 kg payload at 500 bar.
For context on small-scale delivery, DOE's Program Record 20007 (2020) puts combined delivery and dispensing cost for a vehicle refueling station at about $8.17–9.46/kg by gaseous tube trailer, at 1,000 and 450 kg/day station sizes, in 2016 dollars (DOE Program Record 20007). That figure includes 700-bar dispensing, so it is not comparable with bulk industrial delivery, but it shows how quickly small volumes push the cost up.
Worked example: 10 t/day delivered 10–500 km
All inputs below are illustrative assumptions, not quotes, project data or H2Hub outputs. DOE values are used where DOE publishes one.
Stated assumptions:
- Demand: 10 t/day of gaseous hydrogen, 350 operating days a year (3,500 t/yr).
- Finance: 8% discount rate. Trailers recovered over 20 years, tractors 10, compressors 15, pipeline 30.
- Electricity for compression: $60/MWh.
- Truck: DOE trailer payload and capital cost (720 kg; $518,400 per trailer), tractor $200,000, driver cost $45/hour, fuel and maintenance $0.60/km, average speed 60 km/h, 3 hours to fill and 1 hour to swap at the customer, 85% fleet availability and a 20% spare margin. Two DOE terminal compressors at 1.1 kWh/kg, with 2% annual maintenance.
- Pipeline: DOE transmission capital of $765,000/mile ($475,349/km), right-of-way excluded, 2% of capital a year for operation and maintenance, an inlet compressor at $1 million installed with 4% annual maintenance, and DOE's 0.82 kWh/kg.
- Production cost is excluded. Both routes start from the same plant gate.
Results: transport cost per kg
| Distance (km) | Tube-trailer truck ($/kg) | Pipeline, DOE cost ($/kg) | Pipeline, half DOE cost ($/kg) |
|---|---|---|---|
| 10 | 0.47 | 0.24 | 0.17 |
| 25 | 0.54 | 0.46 | 0.28 |
| 50 | 0.65 | 0.83 | 0.46 |
| 100 | 0.87 | 1.57 | 0.83 |
| 200 | 1.31 | 3.05 | 1.57 |
| 300 | 1.75 | 4.53 | 2.31 |
| 500 | 2.62 | 7.48 | 3.79 |
The "half DOE cost" column is a sensitivity, not a forecast. DOE's figure is for an 8-inch-equivalent line, which is far larger than 10 t/day needs, so a smaller line could cost less. Right-of-way, which DOE excludes, pushes the other way.
At 10 t/day, the truck beats a pipeline beyond about 32 km at DOE's cost, or beyond about 111 km at half that cost. Truck cost rises more slowly with distance than pipeline cost because each extra kilometre only adds driver time, fuel and a slightly larger fleet. At 100 km, the truck case needs about six trailer-and-tractor sets making roughly 14 trips a day.
Where the truck money goes
At 100 km, the $0.87/kg truck cost breaks down as about $0.46 driver time, $0.17 fuel and maintenance, $0.09 trailers, $0.05 tractors, $0.07 compression power and $0.04 compressors. Labor, not equipment, is the largest line, which is why payload matters so much: every extra kilogram per trip spreads the driver's hours further.
| Trailer payload | 50 km ($/kg) | 100 km ($/kg) | 200 km ($/kg) |
|---|---|---|---|
| 280 kg (U.S. steel tubes, per IEA) | 1.40 | 1.93 | 2.99 |
| 720 kg (DOE FY2015 status) | 0.65 | 0.87 | 1.31 |
| 1,100 kg (DOE 2020 target) | 0.48 | 0.63 | 0.94 |
When does the pipeline win?
At 100 km, the pipeline's $1.57/kg is almost all capital: about $1.21 of capital recovery and $0.27 of operation and maintenance on a $47.5 million line. That cost is fixed, so doubling the volume halves it per kilogram, while truck cost per kilogram barely moves.
Holding everything else constant, the pipeline becomes cheaper above these volumes:
| Distance | Break-even volume, DOE pipeline cost | Break-even volume, half DOE cost |
|---|---|---|
| 50 km | 13 t/day | 7 t/day |
| 100 km | 19 t/day | 10 t/day |
| 200 km | 24 t/day | 13 t/day |
At 50 t/day, the pipeline costs $0.35/kg at 100 km against $0.86/kg by truck. The volume your offtake contract guarantees is what decides the route, which ties delivery directly to the minimum-take terms covered in our take-or-pay hydrogen offtake guide. A pipeline sized for a buyer that later takes half the volume has doubled its cost per kilogram.
What does this example leave out?
This is a screening model, not a route study. It leaves out:
- Storage at either end. A pipeline running from a variable-output electrolyzer may need buffer storage; trucks need a trailer pool or storage at the customer.
- Right-of-way, permitting and land, which DOE excludes from pipeline capital and which vary widely by route.
- Pressure at the customer. If the user needs higher pressure than the pipeline delivers, another compressor is needed.
- Liquid hydrogen, ammonia and carriers, which matter at longer distances and larger volumes. The IEA notes cryogenic tanker trucks can carry up to 4,000 kg of liquid hydrogen, at the cost of liquefaction.
- Existing infrastructure. Repurposing a gas line or sharing a pipeline with other buyers can change the result completely.
Try it in H2Hub
Start a free H2Hub project for the plant that would supply this buyer, then add the transport line from the tables above to compare the total with the delivered price the buyer is offering. Keep the same demand of 10 t/day and test one change at a time, such as operating hours or power price, to see how much room is left for delivery. If the LCOH build-up is new to you, see what LCOH is and how it is calculated.
You can start without an account or a card. Your first full project and its PDF report are free, and downloading that PDF needs a free sign-in. Re-running with new inputs or adding a second project needs a subscription. Subscribers can explore compression, storage and transport pathways in the Storage & Transport Lab, a subscriber tool.
Pre-feasibility caveat
These figures are screening estimates from public DOE equipment data and stated assumptions. They are not quotes, route studies or engineering advice. Get haulier quotes, a pipeline routing study and qualified engineering review before relying on any delivery cost.
Frequently asked questions
How much does it cost to transport hydrogen by truck?
In our example, compressed-gas tube trailers cost about $0.65–1.31/kg over 50–200 km at 10 t/day, using DOE's 720 kg payload. With 280 kg steel-tube trailers, the same trips cost $1.40–2.99/kg. Real quotes depend on payload, labor rates and how many trips the fleet can make each day.
Is pipeline or truck cheaper for hydrogen?
Trucks are usually cheaper for small volumes and pipelines for large ones. In our example, a new pipeline beats trucks at 100 km once demand passes about 19 t/day at DOE's pipeline cost. The IEA also notes trucks handle most hydrogen distribution today over distances under 300 km.
How much does a hydrogen pipeline cost per km?
DOE's FY2015 status for an 8-inch-equivalent transmission line is $765,000 per mile, about $475,000 per km, excluding right-of-way. DOE's ultimate target is $520,000 per mile. Smaller distribution lines are cheaper per mile.
What is the cheapest way to deliver hydrogen to an industrial site?
In our example, a pipeline is cheapest where the volume is large and steady, while trucks suit smaller or uncertain volumes because they avoid a large fixed investment. Producing on site removes transport entirely, but needs power, water and space at the user's plant. For buyers comparing fuels, our article on hydrogen gas turbine fuel cost shows how a delivered price feeds into a buyer's own economics.
Primary sources and further reading
- International Energy Agency — The Future of Hydrogen, June 2019. Chapter 3: transmission and distribution, trailer payloads and distance thresholds.
- U.S. Department of Energy — DOE Technical Targets for Hydrogen Delivery. Tube trailer, pipeline and compressor status values and targets. Checked 20 November 2026.
- U.S. Department of Energy — Program Record 20007: Hydrogen Delivery and Dispensing Cost, M. Koleva and N. Rustagi, October 2020.
Editorial verification: 20 November 2026. Worked examples are calculations from stated assumptions, not forecasts, market prices or H2Hub-generated results.