Alex Waithera9 min readUpdated

    Hydrogen Project Development Stages: From Screening to FID

    Hydrogen project development stages run from desk screening through pre-feasibility, feasibility and FEED to a final investment decision (FID), and each stage exists to kill weak projects cheaply before the next, larger budget is spent. The IEA says development cycles typically take three to six years, and most announced projects never reach FID.

    In a worked 100 MW example below, a screening-grade estimate puts the cost of hydrogen anywhere between $4.47 and $6.57/kg. A feasibility-grade estimate narrows that to $4.75–6.01/kg. Neither is precise enough to sign a contract on, which is why the stages that follow exist.

    This is general pre-feasibility guidance, not engineering, legal or investment advice.

    What are the hydrogen project development stages?

    A hydrogen project normally passes through five gates, each answering one question before money is committed to the next. Names vary by company, but the logic is the same.

    Stage Question it must answer Typical output
    1. Screening Is there any combination of site, power, water and buyer worth studying? Desk study, first cost range, go/no-go
    2. Pre-feasibility Which configuration and location are best, and could the cost meet a buyer's price? Options comparison, concept-grade cost estimate
    3. Feasibility Can this specific project be built, permitted, supplied and sold? Site-specific design basis, vendor budget quotes, draft offtake and power terms
    4. FEED What exactly will be built, for how much, and on what schedule? Front-end engineering design, EPC pricing, near-final contracts
    5. FID Do lenders, investors and the buyer all sign? Financial close, notice to proceed

    The early stages are cheap and fast; the later ones are slow and expensive. The skill is in stopping a doomed project at stage 1 or 2, not at stage 4.

    How many hydrogen projects actually reach FID?

    Only a small share of announced projects reach FID, and the gap is widening. The IEA's Global Hydrogen Review 2026 reports that new FIDs fell below 0.8 Mt a year of capacity in 2025, after about 1 Mt a year in each of the two previous years, while the announced pipeline for 2030 shrank by 10 Mt to 27 Mt.

    Committed production for 2030 grew only 3%, to 4.3 Mt. The same review warns that more than 100 GW of announced electrolysis capacity could lose any chance of operating by 2030 if FIDs are not taken before the end of 2027.

    The IEA's Global Hydrogen Review 2025 found that half of announced projects already face later start dates than their developers announced, and that more than half of the pipeline had low potential or uncertain operation by 2030. For a developer, the message is that an announcement is not progress. Progress is passing a gate with evidence.

    What must each stage prove before the next one starts?

    Each stage should end with a written go/no-go against criteria set before the work began. The criteria below are the ones that most often decide hydrogen projects.

    Screening. Check that the site has a credible power supply, water, land, grid or transmission access and at least one plausible buyer within reach. Our green hydrogen site selection checklist sets out seven screens. Produce a first levelized cost range and compare it with what buyers in the region pay for their current fuel or feedstock.

    Pre-feasibility. Compare configurations: solar, wind or hybrid supply, electrolyzer size, storage and product (hydrogen, ammonia or another carrier). Rank the inputs that move cost most, using a structured LCOH sensitivity analysis. The stage passes if at least one configuration can plausibly meet a named buyer's price.

    Feasibility. Replace assumptions with site data and counterparties: measured or modelled resource data, vendor budget quotes, a permitting plan, and draft terms for power and offtake. Our guides to the hydrogen power purchase agreement and the hydrogen offtake agreement list the terms that matter at this stage.

    FEED. Fix the design, get firm EPC and equipment pricing, finalize contracts and lock in incentives. This is the stage where development budgets become large.

    FID. Lenders and equity check that revenue, costs, risks and incentives hold up together. If any one of them is still an assumption, the project is not ready.

    How accurate is the cost estimate at each stage?

    Cost estimates get narrower as engineering advances, and the ranges are wider than many pitch decks suggest. The U.S. National Energy Technology Laboratory's cost estimation guidelines (Revision 3, re-issued 2021), which follow AACE International Recommended Practice 18R-97, give an expected accuracy of −25% to +50% for a Class 5 concept-screening estimate and −15% to +30% for a Class 4 feasibility estimate.

    In both classes the possible overrun is twice the possible saving. Estimates from detailed design and FEED narrow further, which is why lenders wait for them.

    Worked example: a 100 MW project at screening and feasibility

    The example applies those two accuracy ranges to the same hypothetical project. All inputs are illustrative assumptions, not quotes, project data or H2Hub outputs.

    Stated assumptions:

    On these inputs the central levelized cost is $5.17/kg: $2.38 for electricity and $2.79 for capital and fixed operating cost. (See our LCOH explainer for how the cost lines combine.)

    Estimate class Installed cost range ($/kW) Hydrogen cost range ($/kg) Width of range ($/kg)
    Class 5, screening (−25% / +50%) 1,500–3,000 4.47–6.57 2.09
    Class 4, feasibility (−15% / +30%) 1,700–2,600 4.75–6.01 1.26

    Suppose a buyer will pay $5.50/kg delivered to the plant gate. At screening, the project could land $1.03/kg under that price or $1.07/kg over it. After feasibility, it is still between $0.75/kg under and $0.51/kg over. The project is worth progressing, but it is not yet bankable.

    Capital cost is only one uncertainty. In the same model, a $10/MWh change in power price moves the result by $0.53/kg, and 1,000 fewer full-load hours raises it by $0.70/kg. Feasibility should attack whichever of these is least certain for your site.

    Where does development money go?

    A second illustrative calculation shows why early gates matter. Assume each stage costs, and passes, as follows: screening $25,000 (40% pass), pre-feasibility $300,000 (50% pass), feasibility $2 million (60% pass) and FEED $10 million (75% reach FID). These are illustrative assumptions, not industry benchmarks.

    Result per project screened Value
    Probability of reaching FID 9%
    Expected development spend about $1.75 million
    Share of that spend in FEED 69%
    Projects screened per project reaching FID about 11
    Development spend per project reaching FID about $19.4 million

    Skipping the cheap screen and sending every idea straight to pre-feasibility raises the spend per FID-ready project to about $21.1 million in this model. The bigger lesson is the FEED share: most of the money at risk is spent at the last gate, so a project that should have failed must fail before FEED, not during it.

    Which deadlines can force the timing of FID?

    Incentive deadlines can set the schedule as much as engineering does. In the United States, the clean hydrogen production credit under 26 U.S.C. § 45V applies only to facilities whose construction begins before January 1, 2028. The deadline was set by Public Law 119-21 of July 4, 2025, replacing the earlier 2033 date (jurisdiction: United States; checked 22 November 2026 against the U.S. Code as in force through Public Law 119-142).

    With development cycles of three to six years, a U.S. project still at screening today cannot plan on 45V unless it can begin construction within about 13 months. That makes the incentive a screening criterion, not a feasibility detail. Confirm what counts as beginning construction with tax counsel.

    Try it in H2Hub

    Take the screening step yourself. Start a free H2Hub project without an account or a card, enter the same 100 MW, $2,000/kW, $45/MWh and 5,000-hour inputs, then change the one number you trust least for your site. Your first full project and its PDF report are free per account, and downloading that PDF needs a free sign-in. Re-running with new inputs or adding a second project needs a subscription.

    How H2Hub works explains the steps. The FID Readiness Lab is a subscriber tool for working through the later gates.

    H2Hub is a screening and learning tool. Its outputs are estimates, not vendor quotations, engineering opinions or investment advice.

    Frequently asked questions

    How long does it take to develop a green hydrogen project?

    The IEA puts typical development cycles at three to six years. Some very large projects in emerging markets take longer: the IEA expects them to operate realistically in 2035–2040, not by 2030.

    What is the difference between pre-feasibility and feasibility?

    Pre-feasibility compares options and asks whether any of them could meet a buyer's price. Feasibility tests one chosen project against real site data, vendor quotes and draft contracts, and should end in a decision to fund FEED or stop.

    What is FEED in a hydrogen project?

    Front-end engineering design fixes the plant design in enough detail to get firm construction pricing and a schedule. That design and price basis is what lenders review at FID.

    What does FID mean for a hydrogen project?

    A final investment decision is the point at which owners and lenders commit construction funding. The IEA treats capacity at FID or under construction as almost certain to operate by 2030.

    Primary sources and further reading

    1. International Energy Agency — Global Hydrogen Review 2026: Production. FIDs in 2025, pipeline and committed production to 2030.
    2. International Energy Agency — Global Hydrogen Review 2025: Production prospects to 2030. Development cycles, delays and pipeline potential.
    3. International Energy Agency — Global Hydrogen Review 2026: Assumptions Annex. Installed electrolyzer cost and efficiency.
    4. U.S. DOE National Energy Technology Laboratory — Quality Guidelines for Energy System Studies: Cost Estimation Methodology, Revision 3 (re-issued February 2021). AACE Class 4 and Class 5 accuracy ranges.
    5. U.S. Code — 26 U.S.C. § 45V, Credit for production of clean hydrogen, checked 22 November 2026.

    Editorial verification: 2026-11-22. Worked examples are calculations from stated assumptions, not forecasts, market prices or H2Hub-generated results.

    Sources

    Explore project tools

    Related articles

    Test your own project assumptions

    H2Hub models power, water and hydrogen costs together — every figure shows its source, date and confidence.