Alex Waithera10 min readUpdated

    LCOH Sensitivity Analysis: How to Stress-Test a Hydrogen Project Before Feasibility

    Illustration of solar panels, wind turbines, an electrolyzer and a hydrogen tank balanced on a tilting seesaw.

    An LCOH sensitivity analysis tells you which assumptions could break a hydrogen project before you pay for a feasibility study. In the worked 100 MW example below, operating hours and power price move the cost of hydrogen most, and moving six inputs to the bad end of their ranges at once takes the cost from $5.72/kg to $8.61/kg.

    Short answer: set a base case, move one input at a time across a range you can defend from public data, rank the swings, then find each input's break point: how far it can slip before the project misses its price. If a plausible slip in one input breaks the project, that input is what the feasibility study must pin down first.

    This is general pre-feasibility guidance, not engineering, investment or financial advice. Confirm all figures with vendor quotations, power offers and qualified advisers.

    The investor's question: do the numbers hold up?

    A pitch deck usually shows one levelized cost of hydrogen (LCOH). An investor or analyst needs to know something different: how wide the honest range is, and which single assumption carries most of the risk. A $5/kg project that becomes $8/kg if the power contract slips is a different investment from one that stays under $6/kg in every reasonable case.

    Our hub guide on what LCOH is and how it is calculated explains the cost lines. This article tests them. The method is simple enough to run before any money goes into a feasibility study, and it tells you which questions that study should answer first.

    Documented inputs and how far they can move

    A stress test is only as good as its ranges. Use ranges you can trace to a source, not round numbers chosen to look reassuring. Public reference data gives a defensible starting point for most inputs:

    DOE's own results show why a single number is not enough. Record 24005 reports roughly $5–7/kg in 2022 dollars, without subsidies, for an installed cost averaging $2,000/kW, renewable power around $0.03/kWh and capacity factors of about 50–75%. Its solar PV case at about 35% capacity factor reaches about $9/kg.

    Worked example: an LCOH sensitivity analysis for a 100 MW plant

    All inputs below are illustrative assumptions, not quotes, project data or H2Hub outputs. The base case is deliberately the same as the 5,000-hour case in our guide to electrolyzer utilization and the cost of hydrogen, so you can compare the two.

    Base case (stated assumptions):

    Base result: about 9,091 tonnes of hydrogen a year at $5.72/kg, made up of $2.46 capital recovery, $0.73 fixed operating cost, $2.20 electricity and $0.33 stack replacement.

    Step 1: move one input at a time

    Each input is moved to the low and high end of a range, with everything else held at the base case.

    Input Range tested Basis for the range LCOH at favourable end LCOH at unfavourable end Swing
    Full-load hours 6,000 to 4,000 ±1,000 hours around base $5.19 $6.52 $1.33
    Power price $30 to $50/MWh ±$10/MWh around base $5.17 $6.27 $1.10
    Installed cost $1,920 to $2,500/kW IEA 2025 global average range $5.31 $6.16 $0.84
    Discount rate 6% to 10% DOE record uses about 10% WACC $5.37 $6.10 $0.73
    Electricity use 51 to 57.5 kWh/kg DOE 2026 target to DOE lifetime average $5.30 $5.98 $0.68
    Economic life 25 to 15 years ±5 years around base $5.52 $6.08 $0.56
    Stack life 80,000 to 40,000 hours DOE target to DOE 2022 status $5.60 $5.80 $0.21

    Sorted by swing, this table is the data behind a tornado chart. In this example, operating hours and power price are the two inputs to pin down first, and stack life barely matters at screening stage. That ranking is specific to these ranges: a wider power-price range or a narrower hours range would reorder it, which is why the ranges must be defensible.

    Step 2: find each input's break point

    A swing shows sensitivity. A break point shows risk. Suppose the project needs hydrogen at no more than $6.72/kg, $1.00 above the base case, to meet a buyer's price. How far can each input slip on its own before the project misses?

    Input Base Break point at $6.72/kg Slip allowed
    Full-load hours 5,000 about 3,807 about 1,190 fewer hours (24%)
    Power price $40/MWh about $58.2/MWh about $18/MWh (46%)
    Installed cost $2,200/kW about $2,889/kW about $690/kW (31%)
    Discount rate 8% about 13.1% about 5 percentage points
    Electricity use 55 kWh/kg about 64.6 kWh/kg about 9.6 kWh/kg (17%)

    Read the two tables together. Power price has a large swing but also a lot of headroom before it breaks the project. Full-load hours combine a large swing with the smallest proportional headroom, so a supply that delivers a quarter fewer hours than planned is enough to miss the price. That is the input to challenge hardest in any power offer. Our guide to the renewables-to-electrolyzer ratio shows how oversizing changes those hours.

    Step 3: test the combined downside

    Inputs rarely fail alone. Moving six inputs to their unfavourable end together (4,000 hours, $50/MWh, $2,500/kW, 10% discount rate, 57.5 kWh/kg and 40,000-hour stacks, with life held at 20 years) gives:

    Cost line ($/kg) Base case Combined downside
    Capital recovery $2.46 $4.22
    Fixed operating cost $0.73 $1.08
    Electricity $2.20 $2.88
    Stack replacement $0.33 $0.43
    Total $5.72 $8.61

    Moving only the three most market-driven inputs (hours, power price and discount rate) gives $7.54/kg. The same six inputs at their favourable end give $3.63/kg. A credible screening result is therefore a range, roughly $3.6–8.6/kg here, with the most likely outcome near the base case and the downside driven mostly by fixed costs spread over fewer hours. Our electrolyzer cost per kW guide explains why installed cost should be tested on a full scope, not an equipment price.

    What this simple stress test leaves out

    This is a one-at-a-time and corner-case test on an annual model. It does not:

    A five-step stress-test checklist

    1. Write down the base case and its sources. Every input should have a source, a date and a range.
    2. Set ranges you can defend. Use published ranges, real quotes and the terms of actual power offers, not ±10% on everything.
    3. Rank the swings. The top two or three inputs are the feasibility study's first questions.
    4. Find the break points against the price the project needs. Small headroom on a big-swing input is the warning sign.
    5. Run the combined downside. If the project only works when everything goes right, say so before anyone commits money.

    Try it in H2Hub

    You can start a project in H2Hub for free, without an account or a card, for the site you are screening. Keep this example's base case beside you: 100 MW, $2,200/kW installed, 5,000 full-load hours, $40/MWh power and 55 kWh/kg, and see where your project's inputs differ.

    Your first full project and its PDF report are free; downloading the PDF needs a free sign-in. Re-running with new inputs, such as the downside power price or fewer hours, or starting a second project requires a subscription, so it is worth choosing your strongest base case first. The LCOH Lab is a subscriber tool for working through cost inputs in more depth; signed-out visitors see an introduction.

    A note on pre-feasibility

    The numbers above are calculations from stated assumptions. They are not forecasts, market prices or H2Hub-generated results, and they do not replace a feasibility study, vendor quotes or financial advice.

    Frequently asked questions

    What is an LCOH sensitivity analysis?

    It measures how much the levelized cost of hydrogen changes when each input changes. The usual form moves one input at a time across a range and ranks the results, often shown as a tornado chart. It identifies which assumptions deserve the most scrutiny.

    Which input affects the cost of green hydrogen most?

    It depends on the project and the ranges tested. In our example, full-load hours and electricity price had the largest swings. DOE's Record 24005 also says LCOH depends strongly on capacity factors and electricity prices.

    How does the discount rate change LCOH?

    A higher discount rate raises the annual cost of recovering capital. In our example, moving from 6% to 10% raised the cost from $5.37/kg to $6.10/kg. Capital-heavy, low-hour projects are the most exposed.

    Should I use Monte Carlo simulation at screening stage?

    Usually not first. Monte Carlo adds probabilities, but its results are only as good as the ranges and distributions behind them. Start with one-at-a-time tests and break points, then add probabilities once the key ranges are backed by quotes.

    Primary sources and further reading

    1. International Energy Agency — Global Hydrogen Review 2026: Assumptions Annex. Electrolysis installed cost and scope, fixed operating cost, stack life; renewable generation costs and full-load hours.
    2. U.S. Department of Energy — Technical Targets for Proton Exchange Membrane Electrolysis, page updated 29 May 2026. System electricity use and stack life, status and targets.
    3. U.S. Department of Energy — Hydrogen Program Record 24005, clean hydrogen production cost with PEM electrolyzers, 20 May 2024. Scenario costs, lifetime electricity use and financial assumptions.

    Editorial verification: 2026-11-10. Worked examples are calculations from stated assumptions, not forecasts, market prices or H2Hub-generated results.

    Sources

    Explore project tools

    Related articles

    Test your own project assumptions

    H2Hub models power, water and hydrogen costs together — every figure shows its source, date and confidence.

    Stress-test your project in H2Hub — start free

    H2Hub produces preliminary project-development analysis. It is not a substitute for licensed engineering, FEED, due diligence or investment advice.