The renewables-to-electrolyzer ratio that gives the cheapest hydrogen is usually above 1, because extra solar and wind let an expensive electrolyzer run more hours, and the wasted power is cheaper than the idle equipment. In the worked 100 MW example below, a hybrid supply reaches its lowest cost near 2.2 MW of renewables per MW of electrolyzer, about $1.92/kg below a 1:1 design.
Short answer: build about 1.5 to 2.5 MW of dedicated solar and wind per MW of electrolyzer as a first screening range, then refine it with an hourly model of your own site. The best ratio rises with electrolyzer cost and depends strongly on location, so no single figure transfers between projects.
This is general pre-feasibility guidance, not engineering or investment advice. Confirm all figures with vendor quotations, a resource assessment and qualified engineers.
The real sizing question
An engineer sizing an off-grid plant has two capacity numbers to set, and they fight each other. A larger electrolyzer captures more of the renewable peaks, but it runs fewer full-load hours. A larger renewable plant fills the electrolyzer for more of the year, but it spills more energy once the electrolyzer is full.
The trade-off is between two costs you pay either way: the fixed annual cost of the electrolyzer and the cost of every megawatt-hour the renewable plant generates, used or not. Our guide to electrolyzer utilization and the cost of hydrogen shows why idle hours are so expensive; this article looks at the most direct way to fix them.
What published studies say
The research agrees on the shape of the answer and disagrees on the number, because the number depends on the site.
- A 2026 UC Merced thesis found that the levelized cost of hydrogen has a convex relationship with the sizing ratio, with an optimum set by the trade-off between curtailment and electrolyzer utilization.
- A 2022 International Journal of Hydrogen Energy paper on off-grid solar and PEM systems found optimal inverter-to-electrolyzer ratios of 1.2 in Atacama, Chile, and 1.4 in Fargo, North Dakota, with further oversizing on the DC side of the solar plant. It reports that low-irradiance locations need larger oversizing.
- A 2026 TU Delft thesis abstract for a 200 MW electrolyzer in the Netherlands reports that the lowest cost came from moderately oversized wind and that the optimal ratio is strongly location-specific.
- A 2024 Energies paper on a wind, solar and underground storage case shows how much revenue treatment matters: oversizing lowered its cost of hydrogen to EUR 4.40/kg without electricity sales and to EUR 2.61/kg with them, from EUR 6.26/kg at its base case.
Definitions vary. Some papers quote electrolyzer capacity divided by renewable capacity, the inverse of the ratio used here, and solar studies may separate DC and AC capacity. Check the convention before comparing numbers.
One large project gives a real-world reference point. The NEOM Green Hydrogen Company describes around 4 GW of dedicated wind and solar, made up of up to 2.2 GW of solar and 1.6 GW of wind, for up to 600 tonnes of hydrogen a day. The project company's page does not state the electrolyzer size, but trade press reports 2.2 GW, which would imply a ratio of roughly 1.7 to 1.8. That is one data point on a very strong wind and solar site, not a benchmark.
Worked example: sizing renewables for a 100 MW electrolyzer
Everything below uses illustrative assumptions, not quotes, project data or H2Hub outputs.
Stated assumptions:
- Electrolyzer: 100 MW, $2,200/kW installed, within the 2025 global average range in the IEA Global Hydrogen Review 2026 assumptions annex
- Fixed operating cost: 3% of capital cost a year (IEA annex)
- Electricity use: 55 kWh/kg, the 2022 system status in the U.S. Department of Energy PEM targets, held constant at all loads
- Stack replacement: $300/kW every 50,000 full-load hours, charged per hour run (stack life from the IEA annex)
- Finance: 8% discount rate over 20 years, capital recovery factor 0.10185
- Minimum electrolyzer load: 10%; energy below it is lost
- Renewable power: a dedicated plant priced at $36.40/MWh, the energy-weighted average of the IEA's 2025 North America values for solar ($37/MWh, 2,480 full-load hours) and onshore wind ($36/MWh, 3,640 full-load hours). It is paid on every megawatt-hour generated, including curtailed energy, with no export revenue.
- Water, oxygen sales, compression, storage, grid connection, taxes and incentives are excluded
Supply profile: a hybrid plant, half solar and half wind by capacity, represented in six output bins per MW of renewable capacity. It totals 3,066 full-load hours, close to the 3,060 implied by averaging the IEA's solar and wind hours.
| Output (share of renewable capacity) | Hours per year |
|---|---|
| 0% | 700 |
| 10% | 1,900 |
| 25% | 2,200 |
| 45% | 1,900 |
| 65% | 1,400 |
| 85% | 660 |
At each ratio, the electrolyzer runs at the lesser of its 100 MW rating and the available power.
Results across the ratio
| Ratio (MW renewables per MW electrolyzer) | Curtailed energy | Full-load hours | Hydrogen (t/yr) | Power | Capital + fixed O&M | Stack | Cost ($/kg) |
|---|---|---|---|---|---|---|---|
| 1.0 | 0.0% | 3,066 | 5,575 | $2.00 | $5.20 | $0.33 | $7.54 |
| 1.25 | 1.1% | 3,791 | 6,893 | $2.02 | $4.21 | $0.33 | $6.56 |
| 1.5 | 3.9% | 4,418 | 8,032 | $2.08 | $3.61 | $0.33 | $6.03 |
| 1.75 | 9.6% | 4,851 | 8,820 | $2.21 | $3.29 | $0.33 | $5.83 |
| 2.0 | 14.4% | 5,250 | 9,545 | $2.34 | $3.04 | $0.33 | $5.71 |
| 2.2 | 17.4% | 5,569 | 10,125 | $2.43 | $2.86 | $0.33 | $5.62 |
| 2.5 | 24.2% | 5,810 | 10,564 | $2.64 | $2.74 | $0.33 | $5.72 |
| 3.0 | 32.8% | 6,180 | 11,236 | $2.98 | $2.58 | $0.33 | $5.89 |
The lowest cost in this example is $5.62/kg at a ratio near 2.2, with 17% of generation curtailed. Moving from 1:1 to 2.2:1 raises the power line by $0.43/kg but cuts capital and fixed costs by $2.34/kg.
Two lessons stand out. First, curtailment is not automatically a failure: spilling almost a fifth of generation is what the cheapest design does here. Second, the bottom of the curve is flat. Between ratios of 2.0 and 2.5 the cost moves by only about $0.10/kg, and this six-bin profile places the exact optimum at a bin edge. Treat 2.2 as a range, not a precise answer.
What moves the best ratio
| Change to the base case | Best ratio | Cost at best ratio |
|---|---|---|
| Base case | about 2.2 | $5.62/kg |
| Electrolyzer at $1,000/kW installed | about 1.55 | $4.03/kg |
| Electrolyzer at $2,500/kW installed | about 2.25 | $6.01/kg |
| Renewable power at $25/MWh | about 2.25 | $4.85/kg |
| Renewable power at $50/MWh | about 2.2 | $6.53/kg |
| Solar only (2,482 full-load hours, $37/MWh) | about 1.7 | $7.12/kg |
The electrolyzer's installed cost is the strongest lever. Cheaper equipment makes idle hours cost less, so the best design carries less oversizing: at $1,000/kW, inside the 2025 range the IEA lists for China, the best ratio falls to about 1.55. For the installed-cost benchmarks behind these cases, see our electrolyzer cost per kW guide.
The price of renewable power barely moves the ratio in this model, which surprises many people, because cost is paid on every megawatt-hour either way. Solar-only supply lands at a lower ratio of about 1.7 because its hours are concentrated in a daily peak and clip quickly.
What the example leaves out
This screening model is built from bins, so it cannot show hourly timing. Before relying on a ratio, check these effects.
- Part-load efficiency. Efficiency usually improves at part load and worsens with degradation; the model holds it constant.
- Minimum load and standby. Higher minimum loads or standby power change what the bottom hours are worth. Our PEM vs alkaline comparison tests how much that matters.
- Delivery profile. A steady buyer may need storage or backup power, which interact with the ratio.
- Export revenue. If curtailed energy can be sold, the optimum shifts toward more renewables, as the Energies paper above illustrates.
- Rules and interconnection. Grid connection, renewable hydrogen rules and generation-site constraints can cap the ratio regardless of economics.
How to use the ratio at screening stage
- Start from demand, then size the electrolyzer. Our guide to sizing an electrolyzer for 10 tonnes of hydrogen a day shows the conversion from tonnes to MW.
- Test a range, not one number. Run ratios from 1.0 to 3.0 and look at where the curve flattens.
- Stop adding renewables when the cost per kilogram stops falling. Curtailment alone is not the signal.
- Rerun with your real quotes. Electrolyzer cost changes the answer more than power price does.
Try it in H2Hub
You can start a project in H2Hub for free, without an account or a card, for the site you are screening. Keep this example's inputs beside you as the baseline: 100 MW electrolyzer, $2,200/kW installed, 55 kWh/kg, $36.40/MWh power and a hybrid wind-solar supply, then compare your project's inputs and see which assumption moves your result most.
Your first full project and its PDF report are free; downloading the PDF needs a free sign-in. Re-running with new inputs, such as a different capacity or power price, or starting a second project requires a subscription, so it is worth choosing your strongest case first. The LCOH Lab is a subscriber tool for working through cost inputs in more depth; signed-out visitors see an introduction.
A note on pre-feasibility
The numbers above are calculations from stated assumptions. They are not forecasts, market prices or H2Hub-generated results, and they do not replace an hourly dispatch study, vendor quotes or financial advice.
Frequently asked questions
What is a good renewables-to-electrolyzer ratio?
As a screening range, about 1.5 to 2.5 MW of dedicated renewables per MW of electrolyzer is a reasonable start. Published optima vary widely by location, resource and whether solar DC capacity is counted separately, so test your own site.
Why oversize solar or wind for an electrolyzer?
Oversizing raises the electrolyzer's full-load hours, which spreads its fixed costs over more hydrogen. In our example that lowered cost from $7.54/kg to $5.62/kg, even with 17% of generation curtailed.
How much curtailment is acceptable?
There is no fixed limit. The right level is whatever minimizes cost per kilogram for your project, and in the example that was about 17% for hybrid supply and about 14% for solar only.
Does a cheaper electrolyzer change the ratio?
Yes. Cheaper equipment reduces the penalty for idle hours, so less oversizing is needed. In the example, dropping the installed cost from $2,200/kW to $1,000/kW moved the best ratio from about 2.2 to about 1.55.
Primary sources and further reading
- International Energy Agency — Global Hydrogen Review 2026: Assumptions Annex. Electrolysis cost and operating assumptions; renewable generation costs and full-load hours.
- U.S. Department of Energy — Technical Targets for Proton Exchange Membrane Electrolysis, page updated 29 May 2026.
- Gallardo et al. — Assessing sizing optimality of off-grid AC-linked solar PV-PEM systems for hydrogen production, International Journal of Hydrogen Energy 47 (2022).
- Clemens et al. — Wind–Photovoltaic–Electrolyzer-Underground Hydrogen Storage System for Cost-Effective Seasonal Energy Storage, Energies 17(22), 2024.
- Dotta Brugman — The Effect of Electrolyzer Sizing and Renewable Resource Complementarity on the Levelized Cost of Hydrogen, UC Merced thesis, 2026.
- van Doorn — Optimal sizing of a hybrid renewable energy system for low cost green hydrogen production, TU Delft thesis abstract, 2026.
- NEOM Green Hydrogen Company — Project overview. Renewable capacity and hydrogen output.
- WaterstofNet (trade press) — 2.2 GW of green ambition: NEOM Green Hydrogen Production Facility, June 2025. Reported electrolyzer capacity.
Editorial verification: 9 November 2026. Worked examples are calculations from stated assumptions, not forecasts, market prices or H2Hub-generated results.
