    Hydrogen Intelligence · Methodology

    How H2Hub verifies hydrogen intelligence

    We do not resell public databases. Every figure in the H2Hub verified layer has been cross-referenced against at least two independent primary sources and reviewed by ReneEnergy technical staff as part of H2Hub's internal data-validation process. That review is a data-quality check — it is not a licensed professional-engineering certification. This page documents exactly how the 2,934 → 160 verification funnel works, who does the work, and what we refuse to publish. Licence terms for each source are listed in the data licensing register.

    Data snapshot:EHO July 2026 · IEA Global Hydrogen Review 2026
    Next refresh:Q1 2027

    The verification funnel

    2,934
    Raw IEA project records

    Global Hydrogen Review 2026 project database (announced through decommissioned).

    1,600+
    Records after de-duplication & normalisation

    Aliased operator names, MW/MWel unit reconciliation, geocoding, product classification.

    398
    Cross-referenced against EHO + press releases

    European Hydrogen Observatory (July 2026) primary + operator-issued FID / commissioning notices.

    160
    H2Hub-verified flagship projects

    Two-source verification of capacity, technology, offtake, timeline; edge cases resolved by manual engineering review.

    See the live figures on the Reconciliation dashboard.

    Process

    1. 1
      Ingest

      IEA GER 2026 project database and EHO July 2026 export are loaded as immutable snapshots.

    2. 2
      Normalise

      Units reconciled (MW vs. MWel vs. t/y H₂), aliases collapsed, geocoding validated.

    3. 3
      Cross-reference

      Each candidate is matched against ≥ 2 independent primary sources: operator press release, FID filing, EHO, or regulator disclosure.

    4. 4
      Technical review

      ReneEnergy technical staff manually resolve conflicts on capacity, technology, and status as part of H2Hub's internal data-validation process. This review is not a licensed professional-engineering certification.

    5. 5
      Publish

      Only fields where two independent sources agree are surfaced in the verified layer; disagreements are logged in the reconciliation dashboard.

    What we refuse to publish

    • Single-sourced capacity claims (press-release-only, no FID or regulator filing).
    • LCOH figures without a documented CAPEX / electricity / capacity-factor stack.
    • "Announced" projects older than 24 months with no construction milestone.
    • Company-supplied numbers that contradict regulator filings without a written reconciliation.

    Who does the work

    H2Hub is built and maintained by ReneEnergy — a systems-first hydrogen engineering practice. We cross-reference published figures against the primary sources listed in the dataset lineage and methodology above, and we apply the resolution rules documented in the verification funnel when sources conflict.

    Refresh cadence

    Verified projects
    Quarterly + on-FID events
    Policy & incentives
    On publication (48h SLA)
    Cost & LCOH benchmarks
    Semi-annual, tied to IEA & EHO releases
    Retired · No longer surfaced on the homepage

    Model card: AI Advancement Classifier (FID-probability framing, withdrawn)

    The homepage previously reported an "FID probability" derived from a binary logistic regression. Our own corpus audit invalidated the framing, so the probability output has been retired. The stage-distribution benchmark that replaced it is documented on the homepage; this card records what the retired model actually was.

    Model
    Multinomial logistic regression, reduced to binary Advanced vs. Stalled.
    Features
    Technology, product, region only. No capacity, CAPEX, power price, offtake or developer signals (all 0% coverage in the source).
    Label
    Current status from the IEA snapshot: Operational / DEMO / FID-Construction ⇒ Advanced; all else ⇒ Stalled. No status transitions were observed.
    Validation
    5-fold cross-sectional CV on the same snapshot: 73.7% accuracy, ROC-AUC ≈ 0.74. No held-out temporal test set.
    Left-censoring
    The observable ~4% cancellation share is severely left-censored — most cancelled projects leave the IEA tracker before appearing here.
    Why retired
    A cross-sectional stage distribution is not a hazard rate. Reporting it as an FID probability implied a forecast the data cannot support.
    Reinstatement criteria
    Requires retrospective IEA vintages (2023–2026) with observed status transitions before any probability output is reintroduced.

    Data: European Hydrogen Observatory (primary) · International Energy Agency (supporting) · Analysis © ReneEnergy.Sources & attribution

    The original publishers have not reviewed or endorsed this analysis.